Tank Farm & Tank Foundation, Gresik Terminal (Package 1)
epcClient: PT Shell IndonesiaYear: 2009
EPCC Package 1 for the Gresik tank farm: six 5,000 m³ vertical storage tanks, two 1,000 m³ tanks, plus tank foundations, bund walls, and drainage systems.
About the project
Consortium of Duta Firza, Intimarindo Primacon, & Bangun Cipta Kontraktor. Contract value IDR 57 billion.
Scope of work
- EPCC (engineering, procurement, construction, and commissioning) for Package 1.
See more projects
Pertamina UPPDN V Surabaya
Fuel & LPG Transit Terminal, Labuhan Amuk, Bali
Full EPC (detailed engineering, procurement, construction, start-up & commissioning) for a strategic fuel and LPG supply hub serving the Bali, NTT, and NTB regions.
View projectPertamina UPPDN V Surabaya
1,000 MT LPG Storage Tank, Labuhan Amuk, Bali
Detailed engineering, procurement, and construction of a 1,000 MT LPG tank to ASME Section VIII Div. 2 for the Bali, NTT, and NTB supply hub.
View projectPT Shell Indonesia
Gresik Terminal Civil & Environmental Infrastructure
Additional scope at Gresik Terminal: HDPE membrane installation, gravel filling, sub-base preparation, and external/intermediate bund wall construction.