Berthing Facility & Jetty Piping, Pulau Laut Oil Terminal
epcClient: PT Indonesia Bulk Terminal (IBT)Year: 2010
EPC marine facilities and pipeline infrastructure: 1 loading platform, 2 breasting dolphins, 4 mooring dolphins, plus piping from battery limit to the loading platform.

About the project
Consortium of Intimarindo Primacon & Duta Firza. Contract value USD 15 million.
Scope of work
- EPC marine facilities: loading platform 15×30 m, breasting dolphins 9×10×2 m, mooring dolphins 7×7×2 m, and jetty piping.
See more projects
Pertamina UPPDN V Surabaya
Fuel & LPG Transit Terminal, Labuhan Amuk, Bali
Full EPC (detailed engineering, procurement, construction, start-up & commissioning) for a strategic fuel and LPG supply hub serving the Bali, NTT, and NTB regions.
View projectPertamina UPPDN V Surabaya
1,000 MT LPG Storage Tank, Labuhan Amuk, Bali
Detailed engineering, procurement, and construction of a 1,000 MT LPG tank to ASME Section VIII Div. 2 for the Bali, NTT, and NTB supply hub.
View projectPT Shell Indonesia
Gresik Terminal Civil & Environmental Infrastructure
Additional scope at Gresik Terminal: HDPE membrane installation, gravel filling, sub-base preparation, and external/intermediate bund wall construction.